Understand the asset as a connected system of infrastructure, operations and access.
Key things to understand
- Always separate the operating Nhon–Cau Giay section from the under-construction underground section.
- Both TBMs completed tunneling in 2026, but tunneling completion is not passenger-service opening.
- The full project is 12.5 km with 12 stations: eight elevated and four underground.
- The February 2026 target for full commercial operation was December 2027; treat it as a target.
- Keep current fares, timetables and ridership dynamic.
- Future Hanoi Station interchange value should not be represented as current operating access.