Infrastructure profile

Nhon–Hanoi Station Metro

Nhon–Hanoi Station Metro is Hanoi's 12.5 km Line 3.1, comprising an 8.5 km elevated section with eight stations from Nhon to Cau Giay and a 4 km underground section with four stations continuing toward Hanoi Station.

Overview

Understand the asset as a connected system of infrastructure, operations and access.

The line must be represented with split status. The elevated Nhon–Cau Giay section has operated commercially since 8 August 2024. The underground section remained under construction in 2026: both TBMs completed the approximately 4 km tunneling journey by April, while Hanoi reported underground construction progress of 79.3% in May. City reporting in February 2026 stated a target of full commercial operation in December 2027; that is a target, not an achieved opening.

Key things to understand

  • Always separate the operating Nhon–Cau Giay section from the under-construction underground section.
  • Both TBMs completed tunneling in 2026, but tunneling completion is not passenger-service opening.
  • The full project is 12.5 km with 12 stations: eight elevated and four underground.
  • The February 2026 target for full commercial operation was December 2027; treat it as a target.
  • Keep current fares, timetables and ridership dynamic.
  • Future Hanoi Station interchange value should not be represented as current operating access.
System perspective

How to understand this infrastructure system

Why it matters

It already provides mass transit to western Hanoi and will become far more useful when the underground section reaches the central city and Hanoi Station.

What makes it distinctive

It is Hanoi's first metro project combining a commercially operating elevated section with a deep underground extension through the historic central area.

What users often miss

A tunnel can be physically bored through while stations and railway systems are still far from commercial opening.

The western half is already carrying passengers; the underground extension to Hanoi Station is still being finished.

System identity

What this infrastructure connects and enables

Core role
Core Function
Provide east–west high-capacity urban rail from Nhon through Cau Giay toward central Hanoi Station.
Network Role
Metro Line 3.1 / pilot urban railway with an operational elevated section and an underground central section under construction.
Economic Role
Supports commuting, reduces road dependence and creates future transfer/TOD opportunities along a major western corridor.
Core Insight
In 2026 the line has two different statuses: Nhon–Cau Giay operates, while the 4 km underground extension to Hanoi Station remains under construction.
Network structure
Total Length
12.5 km.
Elevated
8.5 km with 8 elevated stations, operational since 8 August 2024.
Underground
4 km with 4 underground stations S9–S12 and one emergency shaft, under construction in 2026.
Stations
12 total in the full project.
Central Terminus
Hanoi Station / S12 area when the underground section is completed.
Development

How the infrastructure developed over time

01
2009 onward

Project development

The pilot urban railway is developed with international ODA financing and Hanoi counterpart funds.

02
2010s–2024

Elevated construction and systems

The Nhon–Cau Giay elevated section is completed and tested.

03
From 8 August 2024

Elevated commercial operation

The 8.5 km elevated section with eight stations enters passenger service.

04
2024–April 2026

Underground tunneling

Two TBMs excavate the approximately 4 km underground section through four central stations.

05
2026–2027 target

Underground fit-out and completion

Station civil works, systems, track and integration continue toward the city's target for full-line commercial operation.

2021–2025 programme
Elevated Milestone
The elevated section entered commercial service on 8 August 2024.
Tunneling
TBM work advanced through 2025 and early 2026.
Financing
The project uses ODA from four donors plus Hanoi counterpart funding.
Project Investment
Hanoi reporting in February 2026 gives total investment of VND 34.826 trillion.
Editorial Rule
Never label the full 12.5 km line as fully operational before the underground section is commissioned.
2025 milestone
Elevated
Operational since August 2024.
Underground
Under active construction through 2025 and 2026.
TBM
Both TBMs completed the full underground tunneling journey by April 2026.
Construction Progress
Hanoi reported 79.3% construction progress for the underground section in May 2026.
Interpretation Rule
Tunnel excavation completion does not equal underground passenger opening.
Status guide

How to read operating status

Operational, technically open, under construction, expansion and planned are different states.

OperationalOpen and functioning under normal public operating rules.
Partially operationalOne or more usable sections operate while other sections remain incomplete or under construction.
Under constructionPhysical construction is active and the asset or section is not yet in normal service.
Approved / implementation preparationApproved or assigned for implementation but not yet operating.
PlannedIncluded in a plan but not yet under full construction.
Network anatomy

How the system changes across segments or regions

01

Nhon–Cau Giay

Operational elevated metro serving western Hanoi.

Context

Residential, education and employment catchments.

Watch for

First/last-mile access and interchange quality.

02

Kim Ma–Cat Linh

Underground extension through dense central-west districts.

Context

High urban density and future transfer potential.

Watch for

Construction impacts and station completion.

03

Van Mieu–Hanoi Station

Future central-city underground access.

Context

Historic core, national railway interchange and central employment/tourism.

Watch for

Complex underground construction and urban interfaces.

Design & operations

How design choices shape operation and capacity

Form
Mixed elevated and underground urban railway.
Total Stations
12: eight elevated and four underground.
Operational Section
Nhon–Cau Giay elevated section.
Underground Works
Twin TBM tunnels completed excavation by April 2026.
Fare Technology
Hanoi's metro system moved to identity/biometric and cashless fare technology in 2026.
Operating Rule
Keep current timetable, fares and temporary service conditions dynamic.
User experience

How people use the infrastructure in practice

Traveler use
Current Use
Passengers can use the operational elevated Nhon–Cau Giay section.
Future Use
Do not route passengers through S9–S12 until the underground section officially opens.
Integration
Door-to-door and feeder-mobility integrations are expanding through Hanoi Metro services.
Last Mile
Walking, buses and shared micromobility shape station catchments.
Dynamic Rule
Use current operator information for service hours and fares.
Driving safety
Construction
Central underground station areas require temporary traffic management and work-zone caution.
Rail Safety
Operational passengers should follow platform and train instructions.
Road Interface
Elevated/underground rail reduces direct rail-road conflicts compared with surface railway.
Emergency
Follow operator and station instructions during disruption.
Rule
Do not enter fenced underground construction areas.
Rest areas
Importance
Metro passenger service does not use motorway-style rest areas.
Station Facilities
Passenger amenities are provided through stations and surrounding urban services.
Data Rule
Keep station-specific temporary amenities and outages dynamic.
Tolling
Principle
This is fare-based public transport, not a road toll facility.
Fare System
Hanoi has introduced identity, biometric and cashless fare technologies across operating metro services.
Traveler Rule
Use current Hanoi Metro fare information.
Data Rule
Do not freeze fare tables in stable canonical data.

Before a long drive

  • Use only opened stations
  • Check current service hours
  • Confirm fare/payment method
  • Plan first/last mile
  • Check construction around future underground stations
  • Allow transfer time
  • Follow operator alerts
Economic geography

How connections translate into economic value

Freight & logistics
Role
Passenger urban rail, not freight infrastructure.
Indirect Benefit
Can reduce some commuter road demand and improve worker access.
National Rail Link
Future Hanoi Station terminus can improve passenger interchange with national rail.
Rule
Do not assign cargo capacity to the metro.
Interchange economics
Why It Matters
Transfer and station access determine network value.
Good Node
  • Operational station
  • Safe pedestrian access
  • Bus/micromobility feeder
  • Dense mixed use
  • Future rail transfer
Poor Node
  • Unopened station
  • Long road crossing
  • Weak feeder access
Planning Insight
Keep current and future catchments separate until each station opens.
Industrial investment
Positive Effects
  • Worker accessibility
  • Transit-oriented commercial demand
  • Future central transfer connectivity
Due Diligence
  • Operational versus future station status
  • Walking catchment
  • Pedestrian access
  • Bus interchange
  • Construction impacts
  • TOD rules
Warning
A future underground station should not be valued as current operating access.
Regional effects
Mobility
Creates reliable mass transit along a major western corridor.
Network Effect
Full value rises when the underground central section and other metro lines connect.
Urban Development
Stations can support TOD and pedestrian-oriented development.
Construction Effect
Underground works impose temporary surface disruption in dense central districts.
Caution
Future accessibility benefits must be discounted until commissioning.

Western Hanoi commuters

Operational rail access from Nhon to Cau Giay.

Central-city passengers

Future underground access when S9–S12 open.

Students and workers

Reliable transit along a dense western corridor.

Transit-oriented districts

Improved accessibility around operational and future stations.

Tourism

Faster access changes destination demand

Benefits
  • Operational access along western Hanoi
  • Future central access near major heritage and cultural areas
  • Potential interchange at Hanoi Station
Risks
  • Construction disruption until underground completion
Destination Rule
Use only opened stations in current itineraries.
Capacity & resilience

Where performance, resilience and environmental constraints matter

01

Underground station construction

Complex central-city works can control schedule.

Response

Accelerate fit-out while maintaining safety and quality.

02

Systems integration

Civil completion alone does not create commercial operation.

Response

Complete track, power, signaling, communications and testing.

03

Surface disruption

Work sites affect traffic and businesses.

Response

Shrink barriers and restore surfaces as packages advance.

04

First/last mile

Poor access reduces ridership.

Response

Integrate buses, walking and shared mobility.

05

Network incompleteness

A single partial line has limited transfer reach.

Response

Complete central extension and broader metro network.

Resilience
Power
Reliable traction and station power are essential.
Flooding
Underground stations and tunnels require strong waterproofing, drainage and flood protection.
Heat
Elevated equipment requires heat-resilient maintenance.
Redundancy
Bus and road services provide alternatives during disruption.
Construction
Underground works require continuous geotechnical and settlement monitoring.
Environment
Benefits
  • Electric mass transit
  • Potential reduction in road trips
  • Support for compact TOD
Construction Impacts
  • Excavation
  • Noise and vibration
  • Traffic disruption
  • Spoil management
Mitigation
  • TBM monitoring
  • Surface restoration
  • Noise/vibration control
  • Construction traffic management
System Insight
Long-term environmental gains depend on ridership and integration with the full public-transport network.
Planning & policy
Network Role
Line 3.1 is one of Hanoi's core operating/build-out metro corridors.
2026 Programme
City programmes prioritize operation of Nhon–Hanoi Station and rapid expansion of the wider metro network.
Full Line Target
February 2026 city reporting stated a target for full commercial operation in December 2027.
Integration
Fare and first/last-mile integration are being expanded.
Rule
A target date is not an achieved opening date.
Due diligence

What decision-makers should verify

Decision checklist

  • Identify nearest station and whether it is open
  • Measure walking catchment
  • Review TOD/zoning
  • Account for construction impacts
  • Model future transfer value separately
  • Check feeder services
  • Do not price future access as current access
Interpretation

Common mistakes when reading the infrastructure

Do not assume

  • The full Nhon–Hanoi Station line is not yet operational in 2026.
  • TBM tunneling completion is not commercial opening.
  • The operational section is Nhon–Cau Giay, not all the way to Hanoi Station.
  • The metro does not carry freight.
  • December 2027 is a target, not a completed fact.
History

How the infrastructure reached its current form

2009

Project implementation begins

Hanoi's pilot Line 3 project enters its long implementation period with ODA and counterpart funding.

2024-08-08

Nhon–Cau Giay opens

The 8.5 km elevated section with eight stations enters commercial passenger operation.

2025-02

Second TBM begins its underground drive

TBM 2 starts from S9 toward central Hanoi.

2026-04-13

Full TBM tunneling journey completed

TBM 2 reaches S12, completing excavation through the four underground stations.

2026-05

Underground works continue

Hanoi reports 79.3% construction progress on the underground section.

2027-12 target

Target for full-line commercial operation

City reporting sets December 2027 as the target, subject to completion, testing and commissioning.

Glossary

Useful infrastructure terms

Line 3.1
Hanoi urban railway designation for the Nhon–Hanoi Station project.
TBM
Tunnel Boring Machine used to excavate underground rail tunnels.
Elevated section
Railway carried above ground on viaduct structures.
Underground station
Passenger station built below ground with tunnel connections.
Commissioning
Testing and acceptance process before normal passenger operation.
TOD
Transit-Oriented Development around high-capacity public transport.
Connections

Related infrastructure and places

Cat Linh–Ha Dong MetroHanoi's first operational metro line provides a major public-transport spine west of the centre.
Hanoi National Railway HubHanoi remains the central node of Vietnam's conventional national railway network.
Questions

Frequently asked questions

What is Nhon–Hanoi Station Metro?

Hanoi Metro Line 3.1, a 12.5 km urban railway combining an elevated western section with an underground central section.

How long is the line?

12.5 km.

How much is elevated?

8.5 km.

How much is underground?

4 km.

How many stations are planned in the full project?

12: eight elevated and four underground.

Which section is operating?

The elevated Nhon–Cau Giay section has operated since 8 August 2024.

Is the underground section open?

No. It remained under construction in 2026.

Did the TBMs finish tunneling?

Yes. The second TBM reached S12 in April 2026, completing the tunnel-boring journey.

Does tunnel completion mean the line can open?

No. Stations, track, power, signaling, safety testing and commissioning must also be completed.

What was underground construction progress in May 2026?

Hanoi reported about 79.3% construction progress.

What is the reported total investment?

Hanoi reported VND 34.826 trillion in February 2026.

When is full commercial operation targeted?

City reporting in February 2026 stated a target of December 2027.

Does it carry freight?

No. It is an urban passenger metro.

How are fares changing?

Hanoi is expanding cashless, identity and biometric fare technologies across operating metro services.

What is the main investor caution?

Separate current accessibility from future value around unopened underground stations.

What is the main editorial rule?

Always state the operational elevated section and under-construction underground section separately.

Sources

Primary references

Hanoi People's Committee Portal

Accelerate construction and restore surface to reduce congestion

Source ↗
Hanoi People's Committee Portal

TBM journey through four underground stations completed

Source ↗
Hanoi People's Committee Portal